Start with the finished layout
Give each provider the same selected model, current instructions, measured location, and planned room finish. Ask the heater installer to identify the required air, electrical, piping, drainage, and service-access conditions.
The room contractor should know which finished walls, doors, platforms, or storage arrangements would affect those conditions. The electrician should know the exact model and planned future electrical work. The appropriate plumbing provider should know the final heater location and connection requirements.
Name owners and prerequisites
Create a simple list identifying who performs each task, what must happen first, what is included in its quote, and who pays if the sequence changes. Include equipment removal, gas-related work if applicable, household piping, circuit work, drainage, room corrections, permits, inspections, and finish repair.
Ask who coordinates the schedule and who answers a conflict between trades. “By others” is incomplete unless the other provider, task, and prerequisite are actually named.
Request agreement on which provider confirms the site is ready before installation and which provider authorizes startup. Do not assume the first finished trade is responsible for all remaining work.
Define completion proof
Request relevant inspection records, electrical findings, leak checks, operating verification, manufacturer settings, and owner instruction. Ask for a demonstration of how to access approved care items without moving finished work.
If a trade changes the original layout, have the affected providers confirm the revised plan before closing walls or starting the heater. Keep change costs and responsibility in writing.
Your next step is to ask the project coordinator for the complete sequence and ownership list. Approve the project when the inclusions, dependencies, and final verification make sense together.